Yesterday I met both of these gentlemen and in the 20 minutes we were at the booth we discussed the following;
Had met with Minister Carr and he had inquired what was needed from the federal gov't to make this project happen.
The provincial gov't was in the process of making the application for the billion dollar from the feds to read as to how the funds would be spent.
East/West road route will be determined by end of March with possible extension of 90 days.
Cost projected for the Noront portion was approximately half a billion dollars, with the access roads to the surrounding reserves while not part of Noront concern was another approximate quarter of a billion.
Road to be completed by 2018, Mine to be in operation by 2020.
Glenn meets weekly with the Ring of Fire Secretary and is very positive about the achievement that have derived from this office.