Developing large acreage positions of unconventional and conventional oil and gas resources
Thanks Lanman for the the link to Transerv.com and the reality check. If we follow anything close to this process - the 60 to 90 day rule is back in play!!
The Warro timeline from the first fracture stimulation to the first real flow results shows that testing this first well is very lengthy and complex procedure. In re-reading the Warro 3 results over the past spring and summer it becomes quite a bit clearer how the work done on this first appraisal well may define the work that will proceed with other wells that get drilled at a later date if this one is even moderately successful. Regards Paul