This should help answer your question Aim:
ASSESMENT REPORT
ON THE
DONNAMORE PROJECT
KAMLOOPS MINING DIVISION
BRITISH COLUMBIA
NTS 082M 04
Latitude 51.09055204° North -- Longitude
–119.5632599° West
UTM Zone 11, NAD 83
5663020N 320500E
Prepared for:
INTIGOLD MINES LTD.
#304
– 700 West Pender Street,
Vancouver, British Columbia, V6C 2V6
BY
James Thom, M.Sc.
April 23,
8.0 STATEMENT OF COSTS
Breakdown of Costs for 2012 Exploration work: SOW 5422461
September 18-30 // 14 days
Personnel:
James Thom 14 days @ $750.00 $10,500.00
Gerard Gallissant 14 days @ $350.00 $4,900.00
Trevor Chernoff 14 days @ $350.00 $4,900.00
Ron Boroski 14 days @ $300.00 $4,200.00
Clark Keatings 14 days @ $350.00 $4,900.00
Field Costs:
Field Camp and Supplies 14 days @ $50.00/m/d
(including camp rental, GPS rental, prospecting
and sampling equipment, first aid, generator, field
computer and chain saw)
$3500.00
Field Communications Long Distance charges + Motorola 2 way field
radios
$150.00
Sat phone and costs 1 xks x $150/wk $300.00
Camp Consumables Food/fuels $2777.57
Survey Consumables Sample bags, survey flagging, pickets etc. $700.00
Transportation:
2 x Truck Rental 14 days $300.00/day $4,200.00
2x Quad Rental 14 days $100.00/day $1,400.00
Analytical:
Rock Samples XRF
– 1405 soil samples @ $5.00 per samples
$7,025.00
Office & Engineering:
Report Writing based on results of Phase I exploration program $1,400.00
GIS/Drafting/Cartography $1,400.00
Sub-Total
Total estimate cost of the Phase I exploration program $52,252.57
http://aris.empr.gov.bc.ca/ArisReports/33510.PDF