I looked a bit. I dont think we were trenching before the NR. We got the permit May 2nd and the NR says trenching started the 17 th. Thats a reasonable time to get ready, 2 weeks.
By looking at the May 31 release, we were moving forward at 600m of trenching per week. Using that , we had 9 weeks of trenching at 600m per week, should put us at 5.4 km of trenching. The recommendations were for 5 weeks of trenching. If we did the 9 weeks, it may be suggesting that the company is going above and beyond and getting every bit done that they can as soon as they can. Interesting, if this is the case.
Its 7 weeks since managemenrt had 500 soil samples in their hand, if these were promptly sent to the lab, we are well within the expected time period for results from these. IMO, 6 weeks would have been ample time.