Here's an update to my timeline. Hope it unfolds faster, but these things take time:
drill permit received: beginning of May, 2011
drills mobilized: by end of May, 2011
drilling: June-July, 2011
results sent to lab and analyzed: July-Aug, 2011
assay results released: Sept, 2011
bids for Tesoro from interested parties: Oct-Nov, 2011
evaulation of bids and negotiations with interested party: Dec, 2011 - Jan, 2012
sale of Tesoro: Feb, 2012