Gone, a few months ago I took a stab at what I thought the timeline would look like, and I have updated the timeframe based on (hopefully) getting a permit next week:
drill permit received: end of Feb, 2011
drills mobilized: Mar, 2011 (in the rainy season now - don't know if this will be a concern or not)
drilling: Mar-Apr, 2011
results sent to lab and analyzed: May-June, 2011
assay results released: June, 2011
bids for Tesoro from interested parties: July-August, 2011
evaulation of bids and negotiations with interested party: Sept-Oct, 2011
sale of Tesoro: Nov, 2011