Its my understanding that this is an established drill company in south america. So, they already have drills in the country and have advanced notice of our requirements. I am under the impression that once we receive the permits, the drills should be there within 2 weeks.There will most likely be 2 drills, 1 for shallow holes, and 1 for deep holes.
I beleive a 300m hole should be able to be completed in 1 to 2 weeks, the time will vary because of the rock type. I beleive we should be able to drill a shallow hole in a week, a deep hole,(1000m) 2 to 3 weeks. This is just my opinion, but should give you a time frame.
I would also be interested in what lab we will be using, i asked the question, but at that time I dont think it was determined yet.
So, for a time frame, from permits to first results, I am guessing at least 2.5 months. If the company will report on visible gold in the cores before they are sent to get assayed, this will undoubtedly cause a lot of excitement within that time.