Re: Drilling and Assay Time Reference...
in response to
by
posted on
Jun 11, 2009 09:58AM
Focused on becoming a near-term Gold Producer
Further to this... According to NI 43-101 Jacobus East technicel report released today, dated May 29, 2009...
"20.0 RECOMMENDATIONS:
The Jacobus East Property has produced results which warrant follow‐up sampling and mapping leading to the definition of high‐priority drill targets. The geological setting, mineralization styles and high grade gold abundances are characteristic of Archean‐aged lode gold systems. Early emphasis on establishing drill targets will allow the bulk of sampling and mapping to run concurrently with the drill program. The recommended program (already in progress) will take approximately one month to execute and cost approximately CDN$429,000 (Table 4)."
The recommended program they refer to includes 1,000m... obviouly SGX has already announced they plan to drill 1,500m... so expect 1 month timeline suggested in report to be a little longer. But remember, this 1 month timeline also includes assays. Program (sampling and mapping I would guess) was "already underway" as of date of this report, May 29, 2009. Therefore, my estimate of completion date of July 5, 2009 below may not be that far off... based on this info... everything should may be complete by end of 2nd week of July.... third week latest IMO. Assuming everything runs relatively smoothly of course.
red911
FWIW... About this time in 2007...
re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.
Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).
re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.
Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.
Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.
red911
P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".