Also from todays excellent Newsfest the following was from the 8-K!!
The D-Tree DSO project is on schedule to begin shipping phosphate rock by the end of this year. It is forecast that the project will have an estimated operating cost of A$100-125/tonne FOB (Free on Board) at the Port of Townsville (Queensland, Australia), and the project capital cost is estimated to be A$10-A$15m.
This is great news so I hope the institutions take notice of this info at the BMO Con.