buildout plans to edig, Dec 11 11 per sec exhibit: (sure seems like things got moving after first dec 2 interview!)
Prepared By: Debbe Damron
Date: 12/12/2011
Project: E Digital
16870 W. Bernardo Drive
San Diego CA
Project Number: 8300
HERE IS BUILDOUT HVAC AND ELECTRICAL FOR NEW SPACE...APPARENTLY WE'RE GETTING A "CONTENT ROOM", A "SERVER ROOM" A "LAB"AND A HARD LID ROOM (DON'T KNOW WHAT THAT IS) --AND A DIFFUSER TO ROOM #8
| 15800.000 | HVAC | 350.00 | ||
| Add one duct with diffuser to room #8. | ||||
| 16000.000 | Electrical | 5,250.00 | ||
| 1. Electrical safe off at walls to be removed | ||||
|
2. Install and wire the following switching |
||||
| 3. Install and wire the following outlets | ||||
| a. (3) dedicated outlets in content room | ||||
| b. (3) dedicated outlets in server room | ||||
| c. (1) dedicated outlets in lab | ||||
| d. (3) dedicated for cubes | ||||
| e. (2) dedicated outlets in electric/Mech room | ||||
| 4. Install and wire the following lighting a. (3) relocated existing 2x4 light fixtures |
||||
| b. (3) 6" recessed CFL can lights in new hard lid room | ||||
| 5. Install and wire (1) 100amp 120/208vac 30-circuit panel board fed from existing 200amp panel |
||||