Government fast tracking of a project. In 1988 after a flood disaster in Norther Ontario the Fed. And the Prov. collaborated on relocating Winisk to Peawanuck some 20 miles to the south. Capital project need to go through a process of a Preliminary Project Approval ( where you find a location, do soils, boreholes, water supply, lagoon for sewage collection and any other environmental studies required. The second stage is the Effective Project Approval which allocates and confirms funding of the project. The third stage is tendering of the work. The four stage is construction. The fifth stage commissioning. The consultants on this project and the project management team won a reward for completing the above in one year.