Welcome to the Winfield Stock Hub

Engineering, procurement, construction & management of crude oil refineries.

Free
Message: Itaylor...

Itaylor...

posted on Jun 04, 2008 09:02AM

Do we still expect the $7 Billion dollar refinery to be built in 2 Years?



2 Years to build this behemoth...

Posted by: itaylor on January 20, 2008 05:26PM

Project implementation summary
Progressing ahead of schedule
Milestone Expected
Completion Date
Months from
Zero Date Current Status
Start of the Project / Zero date 1-Dec-05 Started
Technology Selection / Project Scope Jan-06 1 Completed
Completion of Basic Engineering May-06 6 Completed
Order Placement for Critical Equipment May-06 6 Completed
Completion of Detail Engineering Sep-07 22 Completed
Completion of Civil Work Nov-07 24 Advanced stage of completion
Completion of Equipment erection Jan-08 26 On Schedule
Mechanical Completion Aug-08 33 On Schedule
Ready for Start up (RFSU) all areas Sep-08 34 Start-up planning in place
Commencement of Operations Dec-08 36 Operation preparedness ongoing
Share
New Message
Please login to post a reply