Do we still expect the $7 Billion dollar refinery to be built in 2 Years?
2 Years to build this behemoth...
Posted by: itaylor on January 20, 2008 05:26PM
Project implementation summary Progressing ahead of schedule Milestone Expected Completion Date Months from Zero Date Current Status Start of the Project / Zero date 1-Dec-05 Started Technology Selection / Project Scope Jan-06 1 Completed Completion of Basic Engineering May-06 6 Completed Order Placement for Critical Equipment May-06 6 Completed Completion of Detail Engineering Sep-07 22 Completed Completion of Civil Work Nov-07 24 Advanced stage of completion Completion of Equipment erection Jan-08 26 On Schedule Mechanical Completion Aug-08 33 On Schedule Ready for Start up (RFSU) all areas Sep-08 34 Start-up planning in place Commencement of Operations Dec-08 36 Operation preparedness ongoing |