MVEIRB publishes revised workplan for EA for TDC YGP
posted on
Aug 30, 2011 09:58AM
(PRESS PROFILE TAB FOR FACT SHEET & UPDATES)
http://www.reviewboard.ca/upload/project_document/1314301246_Revised_Workplan_for_the_Environmental_Assessment_of_Tyhee_NWT_Corp__s_Yellowknife_Gold_Project.PDF
Just as promised, before the end of August.
Note the revised table at end of document. I am impressed with so many COMPLETED items. The remaining items add up to 13.5 months OR LESS and six TO BE DETERMINED BY THE DEVELOPER items. Many of these items are only IF REQUIRED, such as first and second round of IRs and some public hearings.
This is the roadmap for the final stage in a nearly decade long process, and completion of this ends up in a permit to construct a mine (water use), the ultimate in risk reduction for this stock.
Keep up the good work, DW, progress is clearly being made.
SKELLIG