TYHEE GOLD CORP

(PRESS PROFILE TAB FOR FACT SHEET & UPDATES)

Free
Message: Tyhee's 2009 Annual Report

And for those who just want the the words without the fancy pictures and downloads:

=============================================================

Tyhee has filed applications with the NWT regulatory board for permits to construct and operate a 3,000 tpd mine and mill complex at its wholly-owned Yellowknife Gold Project. Production of 165,000 ounces of gold per year on average, is contemplated from a combined open pit and underground mine.

Gold resources occur in five separate gold zones, all open for expansion with three of the zones providing most of the current resource. All zones outcrop.

Production is expected to initially come from a large open pit on the Ormsby Zone and an underground mine on the Nicholas Lake Zone. The Clan Lake Main Zone open pit mine is scheduled to supply the mill as the Ormsby Zone switches to underground mining.

Ore will be processed at a mill to be constructed near the Ormsby Zone. Gold will be recovered from a conventional crush, grind, gravity, and flotation plus cyanidation circuit. Cost savings occur from using a relatively coarse grind of 150 micron, and a low mass pull from the flotation circuit. Overall recoveries are expected to be in the 95% range.

Additional gold resources occur at the Bruce Zone, adjacent to the Ormsby Zone and the Goodwin Lake Vad Zone, 13 km south of the Ormsby Zone. Undrilled gold zones near the Clan Lake Main Zone have yet to be assessed, and include the Morel, Iceberg and Cub Zones.

Tyhee is transforming from an exploration and development company into a more integrated organization with anticipated gold production. The company continues to build on its dominant position of 10,500 hectares

in the Yellowknife Gold Belt in the Northwest Territories, Canada. A NI 43-101 gold resource of 1.95 million ounces of measured and indicated gold plus 269,000 ounces of inferred gold has been developed for the project. The Big Sky Property is not currently part of the Yellowknife Gold Project but includes an additional 1,990 hectares of mineral claims and mining leases with significant gold showings.

Members of Tyhee’s board and management team have both operated Canada’s most northern gold mine as well as constructed and operated six other gold mines. The development of the Yellowknife Gold Project is progressing as planned after a minor delay due to the severe economic down-turn of late 2008-2009.

A Preliminary Feasibility Study commenced in 2009 should be completed by mid-2010. This study will incorporate the current gold resource, an increased gold price, and other changes in the operating and capital cost structure. Applications for permits to commence construction and operation of a mine and mill complex have been submitted and are part way through that process.

Tyhee is pleased that the Canadian Government understands the potential of Canada’s North. The government’s 2010 budget provides $11 million over two years to Indian & Northern Affairs Canada to support the acceleration of the review of resource projects in the North.

“These reforms will provide clarity and certainty for investors while ensuring that the environment is protected and that Canada’s obligations under existing land claims agreements with Aboriginal groups are respected”,

said the Minister of Finance.

2009 Accomplishments

Tyhee continued with its goal to move the Yellowknife Gold Project to production.

A resource revision in November 2009 expanded the Measured and Indicated gold resource to 1,950,000 ounces and an Inferred resource of 269,000 ounces.

A Preliminary Feasibility Study has been initiated in mid 2009 and is expected to be completed by mid-2010.

A revised Project Description Report was filed with the Mackenzie Valley Land and Water Board in late 2008. The Yellowknife Gold Project was referred to the Mackenzie Environmental Review Board and Scoping Sessions were held to hear comments from the regulators and the public. These comments were incorporated into the Terms of Reference and Work Plan for a Developers Assessment Report(DAR) which was started in 2009 and is expected to be filed in the first half of 2010 Exploration at Clan Lake. An additional six zones have been identified, extending over a 6.5 km strike length, two of which have been drilled in the past.

2010 Goals

Tyhee will continue to revise the resource of its Yellowknife Gold Project as results warrant. Exploration will be focused on Clan Lake in 2010. Clan Lake contains a minimum of six north-northwest striking gold zones within a 1 km wide, 6.5 km long structural corridor. Two of these, the 330 and the Main zones have been drilled, returning exceptional intercepts. Both zones are open for expansion but Tyhee will initially focus on the larger zones. These are the Main, Morel, and Cub Zones. A 10,000 metre program commenced in early 2010 and will continue as results warrant. The initial focus will be a minor gap within the published resource and along strike to the eastsoutheast where an additional 800 metres of surface extent has been identified.

The 2009 fiscal year started off with one of the most significant collapses of world financial markets in history.

The ensuing “flight to safety” resulted in a dramatic drop in equity prices across the board and in all industries.

The Junior Mining sector was hit particularly hard. Tyhee responded by halting any discretionary spending and reducing expenditures to a minimum. By mid-year, the gold markets, which had weathered the downturn better than most, showed tremendous resilience. As a result, Tyhee completed a modest financing to enable the advancement of three critical initiatives.

1. Tyhee commenced a Preliminary Feasibility Study, building on the positive results from the Preliminary Assessment Completed in 2008.

2. Tyhee received its final Terms of Reference and Work Plan from the Mackenzie Valley Environmental Review Board, and commenced completion of its Developer’s Assessment Report.

3. Tyhee conducted additional exploration work on its promising Clan Lake Property.

By the end of 2009, the Company had made significant progress on all three initiatives.

Preliminary Feasibility Study

The Preliminary Feasibility Study is well under way with an established completion date of June 2010. The study includes the 1.95 million ounces of Measured and Indicated gold resource which is 18.7% larger and has a 10% higher grade than the entire Measured, Indicated and Inferred resource in the 2008 Preliminary Assessment.

Continuing metallurgical studies confirm the simple metallurgy of all of the mineralized zones with gold recoveries around 95%.

Discussions are ongoing with the Northwest Territories Power Corporation regarding Tyhee’s operations tying into the grid at Bluefish Power Plant. The tie-in to the grid may reduce operating costs, reduce the carbon footprint, reduce the environmental risk (less diesel fuel to be hauled and stored on site), and lessen the reliance on winter road access.

Permitting

Tyhee had submitted its Project Description Report in August of 2008, and in May 2009, received the Terms of Reference and Work Plan. This “road map” considered input from all relevant regulatory bodies and ministries,

local and aboriginal communities, and will enable Tyhee to address the concerns in its Developer’s Assessment Report. This material report should be ready for submission in June 2010.

Exploration

Tyhee had a very modest exploration program, focused entirely on Clan Lake in 2009. All of the remaining archival drill core had been consolidated, relogged, sampled and incorporated into the database. This enabled the extension of the Main Zone to the northwest and into the Pond Zone, adding 100,000 ounces to the indicated resource.

Prospecting, mapping and sampling further extended the Main Zone to the east/southeast in a series of outcrops. Trenches were blasted into the outcrops to enable proper continuous sampling which demonstrated economically significant grades over substantial widths. Additional sampling and mapping at the other zones refined the geological model on the property and identified drill-ready or near drill- ready targets over a 6.5 km strike-length of prospective ground.

Tyhee remains committed to the Yellowknife Gold Project, which still has many other deposits, and showings to be evaluated. All of the developing gold zones are open in at least one dimension, and other showings are having their geological models refined prior to drilling.

Future Plans

Tyhee expects to reach several milestones this year, including the completion of the Preliminary Feasibility Study and filing of the Developer’s Assessment Report. The ultimate goal, pending positive results, of these two studies is to obtain operating permits and proceed to the decision on construction of a mine and mill complex.

On behalf of my fellow directors I would like to convey our sincere thanks and appreciation to our dedicated team members, past and present, for their contributions and to our shareholders for their continuing support and investment in our exciting future.

Sincerely,

“Dave R. Webb”

Dave R. Webb

President and Chief Executive Officer

Share
New Message
Please login to post a reply