pirquitas is still on schedule

posted on Aug 07, 2008 04:49PM

Pirquitas Mine Construction

The Pirquitas Project is on schedule with plant commissioning to commence in the fourth quarter of this year. The natural gas and water pipelines have been installed, and foundation work is well advanced for the power generating facility. The process plant structural steel installation is progressing on schedule and the truck-shop and warehouse have been completed. The mine operations crews are advancing the open pit pre-stripping and a number of process plant operators have joined the commissioning team and are currently undergoing intensive process training.

http://biz.yahoo.com/iw/080807/04232...