Yeah DC, this was another one of the unfortunate "black holes" where I'm not sure what the correct answer is.
In Monday's breakfast meeting PQ said we should have the cyanide leaching system up in September. I didn't think twice about it because it coincided with when the permitting would be approved. I know Carmine and I both discussed this afterwards when we were reviewing milestones and tried to organize a rough company timeline of things to expect.
Then on Tuesday PQ said it would take 18-24 months to complete and we looked at each other and both said "I thought he said it would be done in September".
I honestly don't know which answer is correct because I don't know how long it normally takes to install a cyanide leaching system. However, it was pretty clear on Tuesday that he stated 18-24 months. I don't know if PQ misinterpreted our question on Monday and gave the answer of when the permitting would be completed (September) when we asked when the system would be completed. I can follow up with him on this.