LongSFMI,
I thought your earlier timetable might be a bit optimistic. I've learned that when I get a time estimate, to triple it and add a week or two. And that's something I learned before I ever invested in SFMI! Seriously, if the building is delivered on Nov 13, with the slab completed and much of the milling equipment already in place, the mill could be up and running by the end of November. As the mill gets closer to completion, the time estimates should get more accurate.
As far as trading, we're back down to average volume today. Looks like the traders may all have taken their profits from the runup. 7 cents may now be the basis for action after the OCTBB listing and events related to mill construction and commissioning.
Looking forward to your site report!
spiny