Considering the guidance given in the April 5th NR
"Replacement and upgrade of the cone crusher, scheduled for early April, combined with the new jaw crusher, are expected to increase mill capacity by 20 to 25 per cent. These improvements are expected to cause five days of downtime for the mill but should not significantly affect second quarter results."
I'd say they delivered.
At the current avg of 1500 t/d and using 1st quarter ounces/t processed, that puts 2nd quarter at about 25k ounces. Keep in mind those 1st quarter numbers included piles and piles of development ore si I wouldn't be the least bit surprised to see 30-35k in the second quarter and push the annual output up over 100k for a 25% increase in their forecast.