Don't remember if I've posted this one before, but anyway ...

Based on :

- spring break up
- estimated frac-time - 2 weeks
- production test - 4 weeks
- using the same frac equipement

...and Talisman's statement that all 4 wells should be completed some place late Q2, early Q3


week 18 spring break up finished

week20 start frac'ing of Gentilly
week 22 start testing of Gentilly
week 23 start frac'ing of LeClercville(not Qec's well)
week 25 start testing of LeClercville
week 26 results from Gentilly
week 26 start frac'ing of Fortierville
week 28 start testing of Fortierville
week 29 results from LeClercville
week 32 results from Fortierville

...off course based on no problems of any sort.