Transeuro Energy Corp. reported today that production at the Beaver River field in British Columbia, Canada
resumed during October after being shut in during the summer due to the low gas prices. The three
production wells, A-2, A-5, and A-7 have been flowing at a reduced rate due to the high pressure in the
main export line. Gross field production in October was 14 mmcf (0.4 mmcm) and in November was 70 mmcf (2
mmcm) or an average of 2.3 mmcf/d (66,000 m3/d). The Company holds a 50% working interest in the Beaver
River Field