Bjorn,
I doubt that you will be seeing any NR on the A-5 well before Christmas. QEC has only recently received regulatory approval for the long-term production tests (initially hoped to have been received by the end of October). I had asked these questions to Mr D'Silva earlier and this was his response:
" We have received regulatory approval for the well in late November. Challenging weather conditions (-20C+ weather and several feet of snow) is hampering the startup of the well and facilities. As soon as we have resolved these issues, we plan to have the well on stream and announce this with a press release."
Johnyboy