Upcoming Milestone Timeline
Timeline Project Milestone
2010 Q2 Late June
|
Strange Lake |
Bench scale metallurgical study by Hazen Research for BZone.
|
2010 Q3 |
Strange Lake |
Starting late June, 13,000 m drilling on BZone to upgrade inferred resource to indicated, and test eastern extension of BZone radiometric anomaly, 2,000 m to test eastern peripheral target, winterized camp allows work until Dec and resume in March 2011.
|
2010 Q3 Early July |
Misery Lake |
Start field work including prospecting and geochem sampling, develop targets for August drilling.
|
2010 Q3 Late July |
Strange Lake |
PEA for BZone.
|
2010 Q3 Late August |
Misery Lake |
Fence of 100 m angled holes totaling 2,500 m on mineralized ring structures after reconnaissance drill released from Strange Lake.
|
2010 Q3 Late September |
Strange Lake |
Delivery to Hazen of 20 tonne bulk sample from BZone for pilot plant scale metallurgical study during 2011 with completion expected late 2011.
|
2011 Q2 Late June |
Strange Lake |
Updated 43-101 resource estimate for BZone incorporating drilling from July-Nov 2010, boost inferred to indicated, include extensions if any.
|