As of the October 4th news release, 18 holes had been drilled at the Friday, while 9 had been drilled at Deadwood.
It takes approximately ten (10) days to drill 1 hole for PEM, so with 1 rig at the FP and 2 at DW, i expect that we are now at 20 holes drilled on the FP and 13 drilled at Deadwood.
These are my estimates.. Lot's of news to come!