APRIL
100G CWDM Solutions TX, RX, TXRX Production in 2H22
100G LR4 Solutions TX, TXRX Production in 2H22
200G CWDM and LR4 Solutions Production in 2H22
400G Solutions DR1, DR4, FR4 Production in 1H23
Custom Light Bar Solutions* Production in 1H23
AUGUST
100G CWDM Solutions TX, RX, TXRX Production in 2H22 on time
100G LR4 Solutions TX, TXRX Production in Q123 Delay of one Q
200G CWDM and LR4 Solutions Production in 2H22 is not shown
400G Solutions DR1, DR4, FR4 Production in 2H23 Delay of 1-2 Q
Custom Light Bar Solutions* Production in 2H23 Delay of 1-2 Q
*Customer schedule
Significant Revenues (whatever that means) coming 2H23 instead of 1H23 which previously we were told is the possible ramp. Until then we are never sure if there is another delay and that is the problem I see here. And in the April Presentation it actually looked like 400G Samples / Custom Light Bar are already in Alpha. (1H22) We really need some regain of trust and get at least these key milestones in Q4.