NI 43-101 Update (September 2012): 11.1 Mt @ 1.68% Ni, 0.87% Cu, 0.89 gpt Pt and 3.09 gpt Pd and 0.18 gpt Au (Proven & Probable Reserves) / 8.9 Mt @ 1.10% Ni, 1.14% Cu, 1.16 gpt Pt and 3.49 gpt Pd and 0.30 gpt Au (Inferred Resource)
Ontario Making Long-Term Investment in Winter Roads Network
January 14, 2021
Energy, Northern Development and Mines
The Ontario government is providing $6 million to the Town of Moosonee and 31 First Nation communities to build 3,170 kilometres of winter roads for the 2020-21 season. The funding will also be used to support special projects, including bridge improvements, maintenance of crossings and other repairs.
The winter road network provides seasonal connections to all-season roads in remote and Far North communities.
Community / Funding Recipient |
Investment |
Project |
Amimakee Wa Zhing #37 (Northwest Angle #37) |
$77,452 |
Winter road from Windigo Island to Kenora |
Bearskin Lake |
$167,117 |
Winter road running northeast from Muskrat Dam to the community |
Cat Lake |
$277,478 |
Winter road running from Pickle Lake to the community |
Deer Lake |
$138,739 |
Winter road running west from North Spirit Lake |
Eabametoong (Fort Hope) |
$173,423 |
Winter road from the community to Kabina Staging Grounds |
Fort Severn |
$368,919 |
Winter road from the community to the Ontario border near Shamattawa, Manitoba |
Kasabonika Lake |
$81,982 |
Winter road from the community to Wawakapewin |
Keewaywin |
$149,775 |
Winter road from the community to the eastern shore of Weagamow Lake |
Kimesskanamenow LP* |
$589,443 |
Winter road from Moosonee to Attawapiskat via Fort Albany and Kashechewan |
Kingfisher Lake |
$291,035 |
Winter road from Kingfisher Lake to North Road Junction (Hwy 599) |
Kitchenuhmaykoosib Inninuwug (KI) |
$192,342 |
Winter road from the community to Kingfisher Lake |
Marten Falls |
$220,721 |
Winter road from the community to Nakina |
Moose Cree |
$15,765 |
Winter road connecting Moosonee and Moose Cree FN |
Town of Moosonee |
$23,561 |
Two ramps required for the winter road to Moose Factory |
Muskrat Dam |
$167,155 |
Winter road from the community to Weagamow Lake |
Neskantaga |
$353,598 |
Winter road from Pickle Lake North Road to Neskantaga |
Nibinamik |
$162,387 |
Winter road from the community to Common Road |
North Caribou Lake |
$126,438 |
Winter road from Windigo Lake to the community and from the community to the west shore of Weagamow Lake |
North Spirit Lake |
$246,447 |
Winter road from the community to the all-season Nungessor Road |
Northwest Angle #33 |
$19,484 |
Winter road from the community to Northwest Angle #37 |
Pikangikum |
$52,027 |
Winter road from the community to the all-season Nungessor Road |
Poplar Hill |
$77,252 |
Winter road from the community to Pikangikum |
Sachigo Lake |
$110,360 |
Winter road running northeast from Muskrat Dam to the community |
Sandy Lake |
$173,423 |
Winter road connecting with the Deer Lake Winter Road System and connecting to Keewaywin Road |
Temagami |
$18,918 |
Winter road from Temagami Access Road to Bear Island |
Wapekeka |
$50,450 |
Winter road from the community to Big Trout Lake Connection |
Wawakapewin |
$195,534 |
Winter road from the community to Highway 599 |
Webequie |
$173,423 |
Winter road from the community to the Nibinamik-Webequie junction |
Weenusk |
$315,316 |
Winter road from the community to Fort Severn |
Wunnumin Lake |
$94,594 |
Winter road from the Assine Lake turn-off to Wunnumin Lake |
* Serves all three communities of Attawapiskat via Fort Albany and Kashechewan