I sent an email to Jim V. of UC Resources (CEO) asking him about drilling costs per meter. He has kindly replied:

--------------------

That's almost impossible to say because of location of drill and chopper time required to get to the drill, and s**t happens in the JBL that happens in remote places.The size of the program and amortizing the mobe and de mobe is a factor as well.

A ball park ??????????? All in $250.00 a meter, is probably safe, but it can get cheaper at times.( no number is safe in the JBL ) In NOT's case the program is so big that in the winter time with little chopper time it could be to $190.00 . Dept of hole and number of moves is also a factor, no it's really a moving target.

Sorry but there really is no number that you can nail down.