Table 2 provides an estimate of the timelines required for the major milestones in this environmental assessment. These are estimated timelines largely dependent on when the Developer’s Assessment Report is received; the work plan timelines will be updated once this occurs.
Table 2 – Estimated Schedule for EA0809-002: Prairie Creek Mine MILESTONE (BOLD TEXT INDICATES COMPLETED STEP) |
Estimated completion |
Bold indicates already completed steps as of April, 2009 |
|
Referral environmental assessment and start-up |
August 2008 |
Scoping Sessions Preparation |
September 2008 |
Scoping Sessions in Dehcho and Yellowknife |
October 2008 |
Scoping Submissions by Interested Parties |
October 2008 |
Request for Ruling on Scope of Development |
March 2009 |
Preparing draft Terms of Reference and Work Plan |
May 2009 |
Comments on draft ToR and Work Plan |
June 12, 2009 |
Final Terms of Reference and Work Plan |
June 26, 2009 |
Developer’s Assessment Report (minimum)2 |
November 2009 |
Review Board Conformity Check and Deficiency Statement (if required) |
November 2009 |
Developer’s response to the Deficiency Statement (if required) |
December 2009 |
Technical Session (DAR gap analysis, if required) |
January 2010 |
First Round IRs |
January 2010- |
Developer’s response to First Round IRs |
February 2010 |
Preparation of Roundtable technical meetings |
February 2010 |
Roundtable technical meetings |
March 2010 |
Second Round of IRs (if required) |
April 2010 |
Responses to Second Round of IR (if required) |
April 2010 |
Parties’ technical reports |
May 2010 |
Pre-hearing conference |
May 2010 |
Preparation for Public and/or Community Hearing(s) |
June 2010 |
Conduct of Public (FS) and/or Community Hearing (NB)3 |
June 2010 |
Undertakings, 3rd Round IRs (if necessary) |
July 2010 |
Closure of Public Registry |
July 2010 |
Review Board Report of Environmental Assessment |
October 2010 |
Review Board’s Report of EA to the Federal Minister |
October 2010 |
Federal Minister’s response to the Review Board’s Report of EA |
--- |
ESTIMATED SCHEDULE