VAL-D'OR, QUEBEC--(Marketwired - Aug. 20, 2013) - Ressources Métanor Inc. ("Metanor") (TSX VENTURE:MTO) is pleased to provide this update on the development activities underway at its Bachelor project.
Metanor produced 2,822 ounces of gold during the month of July. The ounces produced in July came from development and stope ores for a total of 17,403 tonnes of ore at a combined grade of 5.21 grams / tonne with a 96.9% recovery. The grade went up to 5.21 in July, from 5.16 in June, after the commencement of the mining of stope 13-0-02 in the last few days of July, according to preliminary estimates. For instance, the mill produced over 166 oz. per day, during six separate days in the beginning of August, indicating a grade of 7.29 g/t for those days. The actual grade contribution of this stope will be established once the reconciliation of the August production in completed in early September. The tonnage in July is lower when compared to the tonnage in June (20 031 tonnes). This can be attributed to the blasting in early July of a stope which generated larger fragments which in turn slowed down hoisting for a few days. However, fragmentation from blasts which occurred in the last 2 weeks of July generated far better results.
The development on level 10 began in July. The mining activities continued on level 14, 13, 12 and 11 in July. On level 13, the development continued toward the west zone of the mine where an enlargement of the «Main» vein was identified. The long hole production drilling continued in July in three different stopes to eventually have three active stopes. This increase in active stopes will enable the company to increase the tonnage milled per month.
About Metanor
Metanor is a Canadian based gold mining company with a focus on adding value per share through efficient production, exploration, and development of it properties.
Qualified Person