NEWS!
posted on
Jan 07, 2008 05:21AM
Tel: 604-694-2344
NEWS RELEASE 08- 01
Greenwood Gold Project Update
January 7, 2008 – Vancouver. Merit Mining Corp. (TSX-V: MEM) reports that development of theCompany’s Greenwood Gold Project near Greenwood, British Columbia remains on schedule. Mill
start up is planned for the first quarter of 2008 to commence processing of a 10,000 tonne
underground bulk sample from the Lexington-Grenoble mine.
At the Greenwood Gold Project mill, the major pieces of processing equipment are now being installed
including the ball mill, flotation cells, gravity plant, thickener tank and Larox filter. The final concrete
pour for the crushing plant has been completed. The last major pieces of crushing equipment will
arrive on site by the end of January. Power from the main grid was connected to the mill in mid
December by Fortis. Installation of the liner for the Tailings Facility has been completed. Development
work continues underground at the Lexington-Grenoble mine for the extraction of the 10,000 tonne
bulk sample with mining of the initial high grade gold/copper mineralization in progress. Discussions
are underway with respect to an off-take contract for the copper-gold concentrate.
The permit application for full production at 200 tonnes per day was submitted to regulatory authorities
on November 29th, 2007 with the Company’s expectation to go seamlessly into production, upon
completion of the underground bulk sample during the second quarter of 2008. Public meetings are
scheduled for January 23rd and 24th in the local communities of Greenwood and Grand Forks,respectively. The Company has made a number of presentations to the local communities over the
last 5 years with regard to the progress of the Greenwood Gold Project. Consultation with First
Nations, initiated by Merit in April of 2007, is on-going.
Fred Sveinson, President & CEO states “Management is pleased with the progress that Merit’s
construction and development team is making at its Greenwood Gold Project. Our team has worked
closely with the local communities, First Nations and regulatory authorities, employing local residents,
contractors and vendors, wherever possible.”
Merit Mining Corp.
“Fred Sveinson”
Fred Sveinson, President & CEO
For further information please contact:
Fred Sveinson at (604) 694-2344
For Investor Relations Information Contact:
MarketSmart Communications (604) 261-4466
(Toll Free 1-877-261-4466)
The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this
release.
The statements made in this News Release may contain certain forward-looking statements. Actual events or results may
differ from the Company’s expectations. Certain risk factors may also affect the actual results achieved by the Company.
520 - 580 Hornby Street
Vancouver, BC V6C 3B6
Tel: (604) 694-2344 Fax: (604) 642-6577
Email: info@meritminingcorp.com