Message: ICG PEA - Sigma Mill Refurbishment

ron,

- Most recent interview, UTube: Would appreciate if you have a link for this.

- It's true that the Sigma Mill original capacity is 2200 tonnes/day, and this has to be reduced to about half the capacity for the initial phase. They may do it during the second half of the pre-production period to get any kinks out of the system, essentially as a commissioning phase of the mill. They also need the mill to process the bulk samples (no need to pay someone else $46/tonne). Perhaps, efficiency is not a big factor during this phase. They can bring back up the original capacity, if there is enough ore (I think they will have plenty, since the current PEA only use the resources before 24 April 2014).

If they want to increase the mill capacity to the 5000 tonnes/day then they can add a SAG mill.

It looks like it's a flexible and modular design and they can "geared down or up" and do things in stages as far as the mill is concerned. Ditto for the mining, and tailings.

GH