The company is exploring for nickel deposits on its Langmuir property near Timmins, Ontario; for nickel-gold-copper on its Cleaver and Douglas properties; and for molybdenum and rare earth elements at recently acquired Desrosiers property.
I had a look at the MD&A for both quarters…March 31 and June 30 period ending. In both cases, it states we have 3 drills employed at present. We know one is a deep drilling rig. We have yet to see any deep drilling results have we??
-In Q1, it says we drilled 256 holes with 42 being drilled in those 3 months. 17 at Lang No.1 and 25 at Lang No. 2 North
-In Q2, it says we drilled 276 holes with only 19 being drilled in that period. 5 at Lang No.1 and 14 at “Langmuir” (it does not breakdown Langmuir any further)
************************************
Sept 2 Inspiration is continuing the drilling at the Langmuir Project - Langmuir No.2 Mine - North Zone. The detail fill-in drill program is designed to complete the definition of the nickel bearing mineralization below the 100 metre level. The following table indicates the drill information for the North Zone drill holes:
LN08-118 thru 123 (6 holes)
Aug 29 Inspiration is continuing the drilling at the Langmuir Project-Langmuir No.2 Mine-North Zone. The detail fill-in drill program is designed to complete the definition of the nickel bearing mineralization below the 100 metre level. The following table indicates the drill information for the North Zone drill holes:
LN08-115 thru 117 (3 holes)
Aug 19 Inspiration is continuing the drilling at the Langmuir Project - Langmuir No.2 Mine - North Zone. The detail fill-in drill program is designed to complete the definition of the nickel bearing mineralization below the 100 metre level. The following table indicates the drill information for the North Zone drill holes:
LN08-111 thru 114 (4 holes)
July 09 Inspiration is continuing the drilling at the Langmuir Project - Langmuir No.1 Mine. The detail fill-in drill program is designed to complete the definition of the nickel bearing mineralization below the 300-foot mine level to a vertical depth of approximately 900 feet below surface. The following table indicates the drill information for the Langmuir No. 1 Mine drill holes:
L108-111 thru 116 (6 holes)
June 11 Inspiration is continuing the drilling at the Langmuir Project - Langmuir No.2 Mine - North Zone. The detail fill-in drill program is designed to complete the definition of the nickel bearing mineralization below the 100 metre level. The following table indicates the drill information for the North Zone drill holes:
LN08-107 thru 110 (4 holes)
May 22 Inspiration is continuing the drilling at the Langmuir Project - Langmuir No.2 Mine - North Zone. The detail fill-in drill program is designed to complete the definition of the nickel bearing mineralization below the 100 metre level. The following table indicates the drill information for the North Zone drill holes:
LN08-102 thru 106 (5 holes)
May 14 Inspiration is continuing the drilling at the Langmuir Project - Langmuir No.1 Mine. The detail fill-in drill program is designed to complete the definition of the nickel bearing mineralization below the 300-foot mine level to a vertical depth of approximately 900 feet below surface. The following table indicates the drill information for the Langmuir No. 1 Mine drill holes:
L108-107 thru 110 (4 holes)