Dear Fellow Shareholder,
Congratulations on being the first to ask a question in this forum, and please excuse delays in responding, as we are just now starting to use this communication portal.
Our scaling up plan is still to go from pilot (200 TPA) to First Commercial Plant (2,000 TPA), and then to building 10,000 TPA PUREVAPtm QRR reactors.
In actual fact our goal is to have a capacity closer to 22,000 TPA (1 @ 2,000 TPA + 2 @ 10,000 TPA), but we simply rounded down the number to 20,000 TPA in the presentation.
Base on the information we have to date, we believe this to be a realistic and risk adjusted way of moving forward.
I trust this answers your question.
Sincerely,
Bernard J Tourillon CEO
HPQ Silicon Resources Inc
PS please note that in the future our plan is to reply about once or twice per week to general inquiries made though this portal.