Developing Bellechasse-­Timmins Gold Deposit

New Discovery Resulting in a 20KM Mineralized Gold Belt

Free
Message: Response from GNH IR...

Greetings to all,

I emailed Sasha this morning regarding the GNH project in Quebec and he has indicated the following in response:

1) GNH intends to drill enough holes at Bellechasse-Timmins by the end of 2011 to reach their goal of an official resource estimate in early 2012. That remains the plan.

2) A total of 14 holes have been drilled, 5 of which are at Champagne with the rest at Bellechass-Timmins. He cannot comment on time frames for assay results

3) GNH has approximately $1.5M in the bank and $900k due back from the government, meaning there is enough in the bank until a resource estimate is reached.

Thanks,

-Dragon50