Company follows timeline quite well( from Dec 2011)
posted on
Apr 01, 2012 01:10PM
Future Milestones related to the development of the BC Projects are:
Receipt of Environmental Assessment Certificates (“EACs”) for the Tumbler Ridge and Wildmare Projects – 1st Quarter 2012; and the Meikle Project – 4th Quarter 2012
Completion of Turbine Supply Selection Process for the Tumbler Ridge and Wildmare Projects – 1st Quarter 2012
Completion of Design, Build Construction Contracting Process for the Tumbler Ridge and Wildmare Projects – 2nd Quarter 2012
Financial Close for Wildmare and Tumbler Ridge Projects – 2nd Quarter 2012
Partial Notice To Proceed for Wildmare and Tumbler Ridge Construction – 2nd Quarter 2012