Some new photos from August 2012 to go along with some info provided in the 2cd qtr MD&A regarding new equipment for the mill.
Slow but steady progress ....
http://www.dynastymining.com/images/IMGP0147.jpg
http://www.dynastymining.com/images/IMGP0143.jpg
http://www.dynastymining.com/images/IMGP0149.jpg
http://www.dynastymining.com/images/IMGP0151.jpg
http://www.dynastymining.com/images/IMGP0152.jpg
Page 4 of the Q2 MD&A
"A significant improvement the company is currently making to the plant is the construction of a gravity concentration circuit to enable the more efficient processing of material containing high grade coarse gold. To date the Company has constructed and installed the majority of the crucial components of the circuit, including continuous stapes and a large high intensity leaching circuit, to increase the efficiency and is currently estimated to be recovering approximately 90% of the gold entering the circuit. A Falcon concentrator, acquired by the Company from a third party manufacturer, is on location in Zaruma and will be installed in due course. The high intensity leaching circuit will be used with the Falcon to process dore from concentrate on site rather than having to ship concentrate to a third party to be processed."