Welcome to the Crystallex HUB on AGORACOM

Crystallex International Corporation is a Canadian-based gold company with a successful record of developing and operating gold mines in Venezuela and elsewhere in South America

Free
Message: rusoro...dont trust the russians...wheres the P&P?

rusoro...dont trust the russians...wheres the P&P?

posted on Aug 07, 2008 06:41AM

Rusoro Mining Ltd.: 43-101 Report Filed for Isidora and Twin Shear Projects Acquired From Hecla Mining

Additional 482,000 Inferred Au Ounces Identified


Last update: 8:02 a.m. EDT Aug. 7, 2008
VANCOUVER, BRITISH COLUMBIA, Aug 07, 2008 (MARKET WIRE via COMTEX) -- Rusoro Mining Ltd. (CA:RML: news, chart, profile) is pleased to report that a 43-101 report prepared by independent consultants Micon International Ltd. for the Isidora and Twin Shear gold projects has been filed. Both projects were part of the assets acquired in the acquisition of Hecla Mining Company's Venezuelan assets. The total resources outlined in the report for Isidora confirmed the resources originally estimated by Rusoro with the Twin Shear estimation out performing all previous estimates by adding 482,000 Inferred gold ounces to the Company's total resources.
Highlights of the report include;
- Proven and Probable Mineral Reserves at Isidora (March 2008) are 168,000 oz Au (161,900 t @ 32.3 g/t Au). Mineral resources for Isidora are 331,000 oz Au (470,000 t @ 21.9 g/t Au) of Measured and Indicated and 45,000 oz Au (99,000 t @ 14.1 g/t Au) of Inferred.
- Mineral resource for the Twin Shear Zone is 482,000 oz Au (1.2 Mt averaging 12.5 g/t Au) of Inferred.
- The company now has a total of 6.87 M oz Au (84.5 Mt @ 2.52 g/t Au) Measured and Indicated and 6.81 M oz Au (109.6 Mt @ 1.93 g/t Au) Inferred.
Rusoro President, George Salamis, states that, "The Company is very pleased that the overall resource reported in the technical report is more favorable than originally thought. This combined with both deposits being open from an exploration perspective makes both projects very exciting moving forward."
The Mineral Reserves were estimated using a cut-off grade based on actual operating costs from 2007 and were adjusted for production up to March 31, 2008. Total direct operating costs used are $308.98/t of diluted ore with an assumed gold price of $570/oz and a mill recovery of 94.4%.
The Isidora Mine Resources were estimated by mine staff and confirmed by Micon as the independent QP. The estimates were completed using an 8 g/t Au cut-off, a cap of 200 g/t Au with densities of 2.68 for vein material and 2.88 for waste rock. The Twin Shear Resource was estimated by Scott Wilson RPA using a cut-off of 8 g/t Au and a grade cap of 50 g/t Au with a density of 2.7 used for all material.
Mineral resource estimates which are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources in these estimates are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource and it is uncertain if further exploration will result in upgrading them to an indicated or measured category.
Diamond drilling was conducted by independent contractors for Hecla Mining principally using HQ-diameter drill holes. Mineralized sections were split using a core saw and the second half of core remains for inspection and/or additional tests. All sample analyses were conducted by independent contractors using industry standard fire assays. A stringent QA/QC program was utilized including the insertion of standards and check assays for all ore grade samples.
All aspects of the reserve and resource estimates as well as the QA/QC are described in detail in the analysis in the technical report by Micon International with contributions from Scott Wilson RPA for information relevant to the Twin Shear deposit and resource estimate.
Qualified Person: Mr. Gregory Smith, P.Geo, the Vice-President Exploration of the Company, is the Qualified Person as defined by National Instrument 43-101, and is responsible for the accuracy of this news release.
About Rusoro Mining: Rusoro Mining is a junior gold producer with a large land position in the prolific Bolivar State region of Venezuela. The Company operates the Choco 10 and Isidora Mines, processing the ore through the Choco Mill facility near the town of El Callao. The Company has significant 43-101 compliant gold resources and will produce approximately 150,000 oz/Au in 2008. Rusoro is scheduled to drill up to 300,000 meters in 2008 to expand and upgrade its gold ounces for projected production expansion at both the Choco 10 Mill in El Callao and the Emilia Mill in El Dorado where the SREP Mine should be operating by year end.
Share
New Message
Please login to post a reply