From the NR: The Study is expected to be completed on or before May 31, 2014 and is estimated to cost in excess of $1 million to complete. Upon completion of the Study and following presentation, review and acceptance of the Study, Copper Fox expects to sign a facilities agreement whereby BC Hydro would then implement interconnection work, including detailed design and engineering, procurement for major equipment and construction and commissioning of the facilities.
The optimization work by Teck has no defined results or deadlines, so no milestones expected.
At some point they should put together the EA and have it submitted. The road EA might be submitted separately and first.
In terms of CUU we are expecting drill results from AZ, as well as a PEA that I thought was going to come due around the beginning of June.