Here's a summary of the capex costs that were included in the 2008 PFS:
|
Total ($M) |
| Mine Facilities |
50.4 |
| Primary Crushing & Coarse Ore Conveying |
85.8 |
| Coarse Ore Reclaim |
125.9 |
| Grinding & Pebble Crushing |
317.5 |
| Bulk Floatation & Regrind |
133 |
| Copper-Molybdenum Separation |
6 |
| Copper Concentrate |
14.5 |
| Molybdenum Concentrate |
4.1 |
| Tailings Handling |
35.2 |
| Tailings Pond & Water Reclaim System |
17.3 |
| Tailings Impoundment |
173.3 |
| Reagents |
14.6 |
| Plant Services |
33.8 |
| Buildings & Ancillary Facilities |
39.9 |
| Site Development |
264.2 |
| Contracted Directs |
1,315.50 |
|
|
| Common Distributables |
399.1 |
| EPCM |
211 |
| Contracted Indirects |
610.1 |
| Owner’s Cost |
459.8 |
| Subtotal |
2,385.30 |
|
|
| PST Taxes |
28.6 |
| Contingency |
536.5 |
| Total |
2,950.40 |