I took both from the today's NR with the assumption the RE would warrant its own NR:
Resource Estimate -- Preparation of an updated Resource Estimate for the Paramount and Liard zones is currently underway. The Resource Estimate is being performed by Tetra Tech Wardrop (Tetra Tech) and will include all assay results for the diamond drill holes completed in the Paramount and Liard zones at Schaft Creek during the 2011 program. The updated resource estimate will be included in the feasibility study. The 2011 assay results are expected to have a positive impact on the average grade Paramount zone. Additionally Copper Fox has asked Tetra Tech to review the data related to the silver content of the mineralization for possible inclusion in the resource estimate.
Feasibility Study -- Mining Plan -- Copper Fox has been advised by Tetra Tech that due to manpower shortages and scheduling difficulties of staff the March 31st timeline for completion of the Feasibility Study will not be achieved. The main difficulty being encountered lies with the completion of the Mine Plan, the most critical component in the Feasibility Study, which now appears to be six to eight weeks behind schedule. Due to the fact many important components of the Feasibility Study cannot be finalized until the mine plan is completed, a further delay will ensue. It is now expected that completion of the Feasibility study will be delayed until mid-late summer, 2012.