Great Divide |
|
|
|
|
|
|
|
|
|
Application filed |
08/17/05 |
|
|
|
EUB approval letter |
06/29/06 |
|
|
|
Order in Council |
07/13/06 |
10.8 |
|
months from application |
Commenced steam injection |
09/17/07 |
|
|
|
First stage full-time production |
12/19/07 |
17.2 |
|
months from Order in Council |
Pod 1 commerciality |
03/01/08 |
19.6 |
|
months from Order in Council |
Algar |
|
|
|
|
|
|
|
|
|
Application filed |
06/19/07 |
|
|
|
ERCB verbal approval |
10/01/08 |
|
|
|
Order in Council |
11/06/08 |
16.6 |
|
months from application |
Commenced steam injection |
|
|
|
|
First stage full-time production |
|
|
|
|
Pod 2 commerciality |
|
|
|
|